Scope of work
Bathroom remodel: new tile floor, shower walls, vanity and toilet
What's included
- ✓Remove old tile, vanity and toilet, and haul away debris
- ✓Install new tile floor and shower walls
- ✓Install client-chosen vanity and toilet
- ✓Materials up to a $1,200 allowance (contractor buys, client picks)
- ✓Clean-up at the end of each work day
What's not included
- ✕Plumbing or electrical moves (requires a licensed trade, quoted separately)
- ✕Repairs to hidden damage found behind walls or floors
- ✕Permits and inspection fees
- ✕Painting outside the bathroom
Revisions
Material choices are final once ordered. Changes after ordering may add cost and time.
Timeline
About 7 working days once materials arrive.
Fee and payment
$4,800 total. 30% to start, 40% after tile is set, 30% on completion.
Changes and extra work
Any added work is written as a change order with a price, signed before it starts.
Approval
Client signature: ____________________ Date: __________