Motion Graphics Scope of Work Template (Free Example)

Animation is slow to redo, so late changes are costly. A written scope locks the script, the storyboard and the video length, and says when changes stop being free.

Quick answer

Why lock the storyboard before animation starts?

Animation is slow to redo. Changes at the storyboard are cheap and changes after animation are expensive, so the scope should make that clear.

Skip the copy and paste.

Type your messy notes and ScopeFast writes a scope like this one for your project, checks it for risky wording and gives you a ready-to-sign PDF. Your first one is free.

Make my motion graphics & animation scope free →

Example: motion graphics & animation scope of work

Scope of work

A 60-second animated explainer video for a software product

What's included

  • ✓Review and edits of the script (the client provides the draft)
  • ✓A storyboard of 8 to 10 frames
  • ✓Style frames for approval
  • ✓A 60-second animation in 1080p
  • ✓Royalty-free music and sound effects
  • ✓Final files: an MP4 and a square version for social media

What's not included

  • ✕Writing the script from scratch
  • ✕Voice-over recording (available separately)
  • ✕Captions or translations
  • ✕Source project files
  • ✕Extra videos or cut-downs beyond the 2 listed versions

Revisions

2 rounds of changes at the storyboard stage and 1 round after the animation. Changes after approval are billed at $100 an hour.

Timeline

About 5 weeks: 1 week for the storyboard, 1 week for style frames, 3 weeks of animation.

Fee and payment

$5,400 total. 40% ($2,160) to start, 30% ($1,620) at storyboard approval, 30% ($1,620) on delivery.

Changes and extra work

A longer video, new scenes or more versions are quoted in writing first.

Approval

Client signature: ____________________   Date: __________

Tips for motion designers and animators

Questions

Should I hand over the source files?

Only if you agree to it. If not, say that the final videos are delivered and the source files are not included.

Scope creep stops here.

Turn your notes into a professional scope of work in 30 seconds.

Create my free scope →

Get new templates and guides by email

Leave your email and we will send you new scope of work templates and short tips for stopping scope creep. No spam. Reply to any email to unsubscribe.

Client asked for something extra?

Put it in writing before you start. Use a free change order template so extra work gets approved and paid.